S.NO.

ACTIVITY

SPECIFICATIONS

UNIT COST ( )

1.

LAND LEVELLING & SHAPING (2-4% SLOPE)

1 HA (AVERAGE SLOPE 3%, WIDTH OF PLOT (M) 25, EARTH WORK (CU. M.)937.5, LENGTH OF SHOULDER BUND (M):600, EARTHWORK FORSHOULDER BUND (CU .M.):189 )

92,000

2.

LAND LEVELLING & SHAPING (4-6% SLOPE)

1 HA (AVERAGE SLOPE 5%, WIDTH OF PLOT (M) 20, EARTH WORK (CU. M.)1250, LENGTH OF SHOULDER BUND (M):750, EARTHWORK FORSHOULDER BUND (CU. M.):236.25 )

1,20,000

3.

WATER HARVESTING TANK/ JAL KUND – FARM POND

10 X 10 X3CU.M. (EARTH WORK: 300CU. M., ONE PUMPSET,60 PIPES@10 PIPES FOR EACH OF 6M LENGTH )

52,000

4.

WATER HARVESTING TANK/ JAL KUND – FARM POND

5 X 5 X 3 CU. M. (EARTH WORK: 75CU. M., ONE PUMPSET,48 PIPES@8 PIPES FOR EACH OF 6MLENGTH)

32,000

5.

BENCH TERRACING (1HA)

 

 

A.

6 – 10% SLOPE

TERRACE WIDTH: 8M, VERTICAL INTERVAL: 1.41M, LENGTH OF TERRACE 766.87M, EARTH WORK FOR TERRACE FOR 1200CU. M., EARTHWORK FOR SHOULDER BUNDFOR 53.68CU. M.

1,05,000

B.

10– 20% SLOPE

TERRACE WIDTH: 12M, VERTICAL INTERVAL: 1.04M, LENGTH OF TERRACE 1062.7M, EARTH WORK FOR TERRACE FOR 1500CU. M., EARTHWORK FOR SHOULDER BUNDFOR 74.39CU. M.

1,32,000

C.

20– 30% SLOPE

TERRACE WIDTH: 5M, VERTICAL INTERVAL: 1.8M, LENGTH OF TERRACE 1470.6M, EARTH WORK FOR TERRACE FOR 1656CU. M., EARTHWORK FORSHOULDER BUND FOR 102.94CU. M.

1,47,000

5.

CONTOUR CUM FIELDBUNDING (1 HA)

 

 

A.

6– 8% SLOPE

AVE. SLOPE: 7.5%, HORIZONTALINTERVAL: 11M, VERTICAL INTERVAL:0.82M, LENGTH OF BUND: 1140M, EARTH WORK FOR BUND: 718.2CU. M., SOIL & BOULDERSTRUCTURE:`2000

63,000

B.

3– 5% SLOPE

AVE. SLOPE: 4.0%, HORIZONTAL INTERVAL: 20.5M, VERTICAL INTERVAL: 0.87M, LENGTH OF BUND: 610M, EARTH WORK FOR BUND: 384.3CU. M., SOIL & BOULDERSTRUCTURE:`1500

    35,000

6.

VERMI COMPOSTING

3M X 2M X 1M

30,000